26th March 2026
“If you’re entering into a development agreement, either as a contracting authority or with one, the Procurement Act 2023 does not change the need for you to consider whether the agreement is a public works contract. You also still need to assess and document whether your arrangements genuinely meet the new tests for “exclusive rights” and be ready for significantly greater transparency and scrutiny. Getting this analysis right at the outset is critical to avoiding challenge, delay and disruption for all involved.”
If you’re a local authority, registered provider or other contracting authority, or a developer working with one, the lawfulness of your development projects has long sat in a grey area. You’ve often had to make difficult, high‑risk judgments about whether your arrangements amount to public works contracts, whether a compliant procurement process is required and whether the risks are acceptable.
The previous regime required authorities to look at the substance of a transaction and assess whether the main object of a contract was the design/ execution of construction activities or a “work” or the realisation of a “work” corresponding to requirements specified by the authority exercising a decisive influence on the type or design or work.
Case law, a lot of it in the EU courts, had also established a number of issues relevant to this assessment including whether there was an enforceable obligation to deliver the relevant works and whether the authority would receive a direct economic benefit from the works in return for some form of consideration.
The answer in many cases was ‘yes’; for obvious reasons the authority wanted to ensure proper delivery of a project to its own specific requirements and therefore an enforceable works obligation and a decisive influence on design was a necessity.
Authorities sometimes sought to get round this by relying on the “exclusive rights” ground[1] to directly award a works contract on the basis that the authority could not acquire the development site in question unless it also agreed to award the works contract to a specific developer. Sometimes the developer might already own the site but sometimes a “back to back” arrangement would be put in place between the original landowner, the developer and the authority.
Whether the exclusive rights ground applied in either scenario was never tested by the courts and it therefore remained a risk area for authorities, particularly if the authority couldn’t adequately demonstrate that there was no reasonable alternative and that there hadn’t been an artificial narrowing of competition.
PA23 includes a similar “exclusive rights” ground for making a direct award[2]. However, there are some key points you need to know going forward:
So, the answer to the question of what has changed is, in summary, not an awful lot (or at least not yet). It remains to be seen if the new rules will be interpreted differently by the Courts. The issues are still complex, and if you’re involved in a specific transaction, you should take legal advice to assess how the legislative provisions apply to your individual circumstances.
If you have any questions or need support, please contact Kathryn Vickers and our experienced procurement team.
[1] Regulation 32(2)(b)(iii) Public Contracts Regulations 2015
[2] Paragraph 5 of Schedule 5 PA23