27th April 2026
Welcome to the April 2026 edition of Adjudication Matters, where we discuss the latest key developments in adjudication. In this month’s bulletin we look at:
Laing O’Rourke Delivery Ltd v Shepperton Studios Ltd [2026] EWHC 612 (TCC)
Laing O’Rourke Delivery Ltd (“Laing O’Rourke”) was engaged by Shepperton Studios Ltd (“Shepperton”) under a building contract to carry out construction works at the Shepperton Studios site.
Laing O’Rourke submitted an interim payment application seeking £5,627,275.11 plus VAT. In response, Shepperton issued:
Laing O’Rourke commenced an adjudication, arguing that both notices were invalid. The adjudicator agreed, finding that the payment notice failed to provide an adequate breakdown showing how the notified sum had been calculated. Because the pay less notice adopted that same sum as its starting point, the adjudicator concluded it was also defective. Laing O’Rourke was therefore awarded the full amount of its payment application.
Shepperton did not pay and Laing O’Rourke then sought summary judgment to enforce the adjudicator’s decision.
The Technology and Construction Court (“the Court“) was required to consider:
The Court held that:
On the facts, the Court found that Shepperton’s pay less notice contained sufficient detail explaining the deductions it sought to apply. Although it had adopted an incorrect starting figure, this did not deprive it of effect. The judge described the approach as one of substance over form, reflecting the commercial purpose of payment and pay less notices.
As a result, the Court enforced the adjudicator’s decision only to the extent of £3,198,660.64 plus VAT, being the balance once the sums set out in the pay less notice had been deducted rather than the full sum claimed in the application.
Shepperton also sought a stay of execution on the basis that Laing O’Rourke was insolvent, arguing there was a real risk it would not be able to recover any overpayment following final determination of the dispute.
The Court declined to grant a stay. In doing so, it placed weight on:
This case is a timely reminder that:
LMND Group Ltd (“LMND“) and John Henry Group Limited (“JHGL“) entered into a Framework Agreement for the provision of sub-contract services in May 2023 (“the Agreement“). Two sub-contract works directions were issued pursuant to the Agreement, with the works completing in 2024.
This judgment relates to enforcement proceedings arising out of the fifth adjudication brought by LMND, in which LMND sought payment on a notified sum basis in relation to 15 separate applications. The Adjudicator awarded LMND £238,000.
JHGL resisted enforcement on the basis of two alleged breaches of natural justice, relating to the Adjudicator’s treatment of defences that JHGL had raised:
The Court dealt with each alleged breach in turn.
The Court held that the Adjudicator’s rejection of JHGL’s Estoppel Defence relied on reasoning and authority that neither party had advanced nor been invited to address.
In particular, the Adjudicator relied on the case of Spencer V MW High Tech Projects Ltd[1] (“Spencer”) to support the proposition that a shared misunderstanding of the applicability of the Housing Grants, Construction and Regeneration Act 1996 (the “Construction Act“) could not create an estoppel by convention. Spencer had not been referenced by either party, nor put to them for comment, before being relied upon in the Adjudicator’s decision.
LMND argued that the reference to Spencer was merely for completeness and had not impacted the Adjudicator’s rejection of the Estoppel Defence however, the Court rejected this, finding that the Spencer case played a determinative role in the Adjudication’s decision.
The Court held that this constituted a serious breach of natural justice and that the breach had a material impact on the outcome of the adjudication. Enforcement of the Adjudicator’s Decision was, therefore, refused.
The Court dealt with the second challenge briefly and ultimately rejected it, holding that the Adjudicator had reached a conclusion which was open to the Adjudicator to make.
Further, the Adjudicator was correct to determine that, in the context of a notified sum adjudication, arguments relating to double payment could not be considered where the notified sum had not first been paid.
This judgment provides a rare example of a successful natural justice challenge to enforcement.
It provides a reminder that, whilst the Courts remain firmly pro-enforcement, adjudication enforcement disputes are highly fact sensitive and procedural missteps can be fatal.
Adjudicators are entitled to apply the law but, where a point of law is potentially determinative and has not been raised by the parties, submissions should always be invited from the parties before the Decision is made.
If you have any queries about this bulletin or would like to know more about adjudication, please contact Carly Thorpe, Juliet Gough or Isabella Troy-Williamson.
If you’d like to receive this and other similar updates direct to your inbox, please click the link here.
Explore our Adjudication Basics video series here.