29th April 2025
“Grid connection reform – a key tenet of the UK government’s net zero and growth ambitions – continues accelerating. With Ofgem confirming approval of TMO4+ and NESO publishing its final Gate 2 Methodologies, we provide the latest update on what this means for developers, funders, and the broader energy sector.”
On 15 April 2025, Ofgem approved the TMO4+ package, and NESO published the final Gate 2 Methodologies, marking a significant milestone in the UK’s ambitious reform of grid connection processes. These announcements confirm the new framework through which existing and new projects will be assessed and prioritised for connection.
While this is a welcome step forward, it comes with caution: implementation begins a much longer journey to a fully reformed grid queue. The effectiveness of this transformation will depend on how well the new application processes integrate and how many projects ultimately achieve connection under the new regime.
Key upcoming dates now confirmed:
These confirmed milestones provide much-needed certainty to developers currently navigating the evolving landscape of grid connection reform. NESO’s methodologies provide a clearer path for how projects will be assessed for inclusion in the queue — introducing criteria around readiness, strategic alignment, and ongoing milestone compliance. Only those that meet these standards will secure firm connection dates.
Queue Management Milestones aim to keep the queue healthy and progressing timely.
Consultation continues in relation to NESO proposals for the implementation of the Progression Commitment Fee (PCF), which is expected to conclude and be referred to Ofgem for a decision in July. The PCF aims to ensure only viable projects progress.
Importantly, projects with existing grid offers will need to reapply through the Gate 2 window. ‘Protected Projects’ — including those with connection dates on or before 31 December 2026 or with certain milestones already achieved — may receive priority access. In its decision document, Ofgem has recommended that additional assurances are extended to projects with connection dates on or before 31 December 2027.
With the confirmation of these methodologies, NESO has cemented the transition from a ‘first come, first served’ approach to one focused on strategic value and project readiness.
This includes:
As NESO prepares to reorder the queue and initiate the new offer process, the clarity of these confirmed timelines enables developers and funders to plan more confidently.
These latest updates bring both clarity and complexity. Here’s what developers and funders need to know:
Confirming TMO4+ and NESO’s methodologies marks a major step toward a smarter, fairer, and more strategic connection process. But it’s not the destination. The system now needs to prove it can deliver — not just reallocate — capacity.
We anticipate this will drive:
The winners will be those who act early, align with strategic objectives, and demonstrate project maturity. The losers may find themselves sidelined in an increasingly competitive and performance-driven system.
Our Infrastructure & Energy Group advises developers, funders, and stakeholders on all aspects of grid reform, from understanding the Gate 2 criteria and designation process to managing PCF risk and preparing for offer reapplication.
Please get in touch with Shane Toal or Paul Dinning to discuss any questions you may have.
Further information is available via Ofgem’s formal decision here: https://www.ofgem.gov.uk/decision/decision-connections-reform-package-tm04
Read our previous article on grid connection reform here: Grid connection reform: Transforming energy and infrastructure development – Walker Morris