Public Procurement Update

In their latest update, Walker Morris commercial dispute resolution and procurement specialists Lynsey Oakdene and Kathryn Vickers consider proposed reforms; recent notable decisions on expert evidence, expedited trials and limitation; and provide an update on other developments.
How we can help
Walker Morris is experienced in dealing with public law issues including procurement law and is also regularly instructed to provide advice on an urgent basis on procurement challenges. If you need any advice or assistance, or have any queries concerning the points raised in this update, please contact Lynsey or Kathryn, who will be very happy to help.

Government responds to ‘Transforming public procurement’ Green Paper
On 6 December 2021, the government published its response to the ‘Transforming public procurement’ Green […]
On 6 December 2021, the government published its response to the ‘Transforming public procurement’ Green Paper consulted on between December 2020 and March 2021. A summary can be found in the ‘Key themes’ section on pages 6 to 8. Among other things, the government intends to introduce a new exclusions framework which will be simpler, clearer and more focused on suppliers who pose an unacceptable risk to effective competition for contracts, reliable delivery, and protection of the public, the environment, public funds, national security interests or the rights of employees.
The new public procurement regime is unlikely to come into force until 2023 at the earliest. Walker Morris will continue to monitor and report on key developments.
In our earlier briefing, we looked at the proposals for fair and fast challenges to procurement decisions, which included capping the level of damages available to aggrieved bidders to legal fees and 1.5 x bid costs, reducing the attractiveness of speculative claims. The government has decided not to proceed with that proposal. It is also not intending to go ahead with a process of independent contracting authority review, or with the idea of using an existing tribunal to deal with low value claims and issues relating to ongoing competitions. The objectives of a faster and simpler court process are targeted instead through the planned introduction of intended reforms to processes such as decisions on written pleadings, early and enhanced disclosure and a dedicated procurement judge.
The proposal that pre-contractual remedies should have stated primacy over post-contractual damages will not be introduced, partly because of the decision not to pursue the damages cap, but also because there will be more opportunity for pre-contractual remedies in a quicker system where the impact of delay is not so great as with current court timescales.
The government intends to introduce a new test into legislation on the lifting of automatic suspensions, believing that it would be helpful to all parties to clarify the test for use in a procurement-specific context. The government is still working through the potential options but envisages that the new test will be a simple, single limb test which provides for suspensions to be lifted where there are overriding consequences for the various interests concerned. This will include the impact on public service delivery.
The government also intends to proceed with the proposal that removal of automatic suspension is appropriate in crisis and extremely urgent circumstances to encourage the use of informal competition. It agrees that the terms for urgent contracting need to be clear, measured and proportionate. There will be a requirement for a notice prior to (or concurrent with) contract award which will ensure greater transparency and scrutiny of contracts relying on these measures for extreme urgency. This will be followed up by the publication of a notice containing details of the contract. Due to the absence of a standstill requirement with these contracts, the remedy of ineffectiveness will remain available where suppliers can show that the grounds have been relied upon inappropriately.
As to whether debrief letters need no longer be mandated in the context of the proposed transparency requirements in the new regime, the government intends to go ahead with this proposal, but with some amendments to seek to address various stakeholder concerns.

Update on judicial review reform
We referred in our previous update to the contentious Judicial Review and Courts Bill which […]
We referred in our previous update to the contentious Judicial Review and Courts Bill which was introduced to Parliament in July 2021. Having started in the House of Commons, the Bill is now being considered in the House of Lords with report stage – a further chance to closely scrutinise elements of the Bill and make changes – scheduled for 28 March 2022.
The Law Society’s head of public law gave oral evidence to the Public Bill Committee in which she outlined the Law Society’s priority concerns regarding: the introduction of prospective-only quashing orders, which the Law Society says would deny remedy to people affected by previous exercises of an impugned (i.e. challenged) power; and the inclusion of a statutory presumption in favour of using suspended or prospective-only quashing orders over an ordinary quashing order, which it says would limit judicial discretion and remedial flexibility.
On 7 December 2021, the Joint Committee on Human Rights published a report recommending amendments to the Bill. Among other things, the Committee’s Chair said that the Bill “dilutes the power of the courts to order redress and should be amended. The plan to carve out further areas from judicial review scrutiny should be resisted”.
More recently, the House of Lords Constitution Committee published a report in which it says that the House of Lords may wish to consider whether the proposed clause providing that courts may issue suspended quashing orders and prospective-only quashing orders achieves the correct balance between providing them with discretion and placing a presumption on how they should act. Additionally, that the House of Lords may wish to explore the relationship between that clause and Article 13 of the European Convention on Human Rights – the right to an effective remedy.
Walker Morris will continue to monitor and report on key developments.

Expert evidence requirements “not optional extras”
Permission of the court is required for expert evidence and the court has a duty […]
Permission of the court is required for expert evidence and the court has a duty to restrict it to that which is reasonably required to resolve the proceedings. In addition, an expert must comply with the requirements of Part 35 of the Civil Procedure Rules (CPR) and the associated Practice Direction.
The decision in R (Good Law Project Ltd) v Secretary of State for Health and Social Care) [1] serves as a cautionary reminder to experts, and the advisers instructing them, of the importance of fully familiarising themselves with the requirements and complying with them. The court refused the Secretary of State’s application to adduce expert evidence in a judicial review claim due to a widespread failure to observe the requirements, in particular that experts for both parties must have access to the same material.
The court stressed that the requirements are not optional extras, only to be complied with by a litigant and their expert if the court states in a specific case that they are to apply. There is no excuse for litigants to fail to comply with the rules generally, nor for failures by experts to comply with the requirements of CPR Part 35 specifically. Parties in judicial review proceedings are not entitled to some wider indulgence, nor are the rules to be applied less strictly simply because a case concerns public law. The court also noted that there is a duty of candour in judicial review proceedings generally. See our separate briefing for details.
[1] [2021] EWHC 2595 (TCC)

Automatic suspension maintained pending expedited trial
In Vodafone Ltd v Secretary of State for Foreign, Commonwealth and Development Affairs and another […]
In Vodafone Ltd v Secretary of State for Foreign, Commonwealth and Development Affairs and another [1] the court held that the balance of convenience lay in maintaining an automatic suspension pending the expedited trial of a preliminary issue to take place in January 2022. The Secretary of State applied to lift the automatic suspension under public procurement regulations of the power to award a contract for the provision of a replacement secure electronic communications system to the successful tenderer, Fujitsu. Vodafone, one of the unsuccessful tenderers, applied to the court for a direction that there should instead be an expedited trial of a preliminary issue, i.e. whether the defendants acted unlawfully in abridging the timetable of the public procurement exercise and awarding the contract on the basis of initial tenders only, without further negotiation.
The well-known American Cyanamid tests [2] applied to whether the automatic stay should be lifted. The defendants accepted that there was a serious issue to be tried as to whether the decision to appoint Fujitsu was, in some way, unlawful. The court decided it would not be just to confine Vodafone to its remedy in damages in light of the unquantifiable loss of opportunities to bid for and win other contracts on the back of this one.
If it were just a matter of money, damages pursuant to Vodafone’s standard undertaking might well have been adequate to compensate the defendants if it turned out that the automatic stay was wrongly kept in place. The court was inclined to conclude that damages would not be an adequate remedy for the defendants – the sooner the replacement system was implemented, the safer the country would be, and the security and reputation of the UK could not be measured in money terms.
However, the evidence of perceived threat levels and on timing had to be taken into account. It was striking that there was no evidence that any specific security threat had been linked to the outdatedness of the current system. If the preliminary issue was a viable solution, prejudice to the defendants arising from the automatic stay would be time limited, since it would be lifted if Vodafone lost on the preliminary issue. The defendants would be adequately protected by Vodafone’s undertaking in damages, if but only if the preliminary issue trial was a viable proposition.
While the preliminary issue was not a perfect solution, it was a viable one, and the one causing the least irremediable injustice. The matter was fit for expedition and the balance of convenience and justice came down in favour of maintaining the automatic stay until the preliminary issue had been tried.
Having considered its powers under the regulations, the court also made an interim order modifying the requirement not to enter into a contract, so that the defendants, in advance of the preliminary issue trial, might enter into a conditional contract with Fujitsu. The court accepted that this provided them with only limited comfort during the period leading up to the trial in January 2022 and that Fujitsu might not be willing to enter into such an agreement.
[1] [2021] EWHC 2793 (TCC)
[2] Recently formulated in the Draeger case (see our previous update): When determining an application to lift the automatic suspension in a procurement challenge case, the court must consider the following issues:
(i) Is there a serious issue to be tried?
(ii) If so, would damages be an adequate remedy for the claimant if the suspension were lifted and they succeeded at trial; is it just in all the circumstances that the claimant should be confined to its remedy of damages?
(iii) If not, would damages be an adequate remedy for the defendant if the suspension remained in place and it succeeded at trial?
(iv) Where there is doubt as to the adequacy of damages for either of the parties, which course of action is likely to carry the least risk of injustice if it transpires that it was wrong, that is, where does the balance of convenience lie?

An important lesson in getting limitation right
In Access for Living v London Borough of Lewisham [1] the court refused to grant […]
In Access for Living v London Borough of Lewisham [1] the court refused to grant an extension of time where the claimant’s solicitor had mistakenly equated a standstill for the purposes of contract award under the Public Contracts Regulations 2015 with a standstill for limitation purposes. The parties agreed to extend the automatic ten day standstill period during which the defendant could not enter into new contracts. By the time the claimant issued proceedings within that extended time period, the 30 day limitation period had already expired and the claimant applied to the court for an extension of time.
The court may extend the 30 day time limit (up to a longstop of three months) where it considers that there is “good reason” for doing so. The court picked out the following key principles from the line of previous cases:
- There is no exhaustive list of factors that may (or may not) be a good reason to extend time. The list is open-ended.
- Matters that are at the very least unlikely to be considered by the court to be a good reason include ignorance of the law, commercial considerations, carelessness including by lawyers, lack of urgency and engagement in pre-action investigations or correspondence.
- One matter that is clearly not in itself a good reason to extend time is that the extension sought is a short one. Where there is some other good reason to extend time, the shortness of the extension may be a relevant factor but it is not sufficient in itself.
- Similarly lack of prejudice to the defendant is not in itself a good reason to extend time although it may be a relevant factor.
- A matter that is beyond the control of the applicant may well provide a good reason. While this is the only commonplace situation that the courts have identified as one where there would be a good reason to extend time, that does not preclude there being other factual situations in which there is a good reason to extend time.
This decision highlights to parties, and their advisers, the importance of paying strict attention to procedural requirements and timescales.
[1] [2021] EWHC 3498 (TCC)

New greener rules for major government contracts
New rules set out in Procurement Policy Note 06/21 were introduced on 30 September 2021 […]
New rules set out in Procurement Policy Note 06/21 were introduced on 30 September 2021 requiring any businesses (not just those that are successful) bidding for government contracts worth more than £5 million a year to commit to achieving net zero emissions. The UK is the first country to introduce such a measure. Bidding suppliers are required to provide a ‘Carbon Reduction Plan’ confirming their commitment to achieving net zero by 2050 in the UK, and setting out the environmental management measures they have in place and which will be in effect and utilised during the performance of the contract. In completing their Carbon Reduction Plans, suppliers are required to detail certain Scope 3 emissions including business travel and employee commuting. See the press release.
In related news, the Local Government Association published a sustainable procurement toolkit for commissioners, procurement practitioners and contract managers to deliver local, economic, social and environmental priorities.

Other recent developments
Amendments made to UK public procurement regulations to update certain financial thresholds which govern the […]
Amendments made to UK public procurement regulations to update certain financial thresholds which govern the procedures for the award of public contracts for goods, works and services came into force on 1 January 2022. There was also a change to the calculation of the estimated value of a procurement based on the total amount payable without making a deduction for VAT, in order to fully implement the UK’s obligations under the World Trade Organisation’s Agreement on Government Procurement.
The Cabinet Office published Procurement Policy Note (PPN) 08/21 on taking account of a bidder’s approach to payment in the procurement of major government contracts. The note applies in respect of all procurements above £5 million per year, advertised on or after 1 April 2022. It replaces PPN 07/20, the key update being the increase to the threshold bidders have to meet to demonstrate they have effective payment systems in place to ensure the reliability of their supply chains.
PPN 09/21 reminds in-scope organisations of the requirements to publish procurement information on Contracts Finder. The Note and associated guidance replace PPN 07/21 and clarify requirements on NHS Foundation Trusts. There is no change to the publication requirements for other contracting authorities that were set out in PPN 07/21.
The Cabinet Office also published a guide providing advice for SMEs on how to bid for and win government contracts.